Work Performed, September 11th to September 15th
·
Work performed along Hudson Road, York Road, and
Raleigh Road (south end to York Road):
o Continued
rough grading of landscape behind the curb & gutter
o Fine
graded aggregate base of roadway
o Paved
first binder layers of new asphalt pavement
o Install
2nd layer of asphalt for driveway restorations.
o Access
to driveways restored (Friday, September 15th)
·
Completed roadway excavation and installation of
base course along Raleigh Road from Baffin Road to Glenview Road
·
Continued roadway excavation and installation of
base course along Baffin Road
·
Continued miscellaneous underground utility
relocations and adjustments for sanitary sewer, storm sewer, and water main.
Work Anticipated to be performed, September 18th
to September 22nd
·
Work to be performed along Raleigh Road from
York Road to 200 feet north of Drake Road:
o Access
to driveway restricted: Tuesday, September 19th at 7:00 AM
o Installation
of string line for concrete curb & gutter
o Grading
aggregate base under curb & gutter
o Pour
concrete curb & gutter (Scheduled for Thursday, September 21st)
o Rough
grade landscape behind curb & gutter
o Restore
asphalt driveways (1st Layer of asphalt)
o Fine
grade roadway base
o Pave
first layer of asphalt pavement (Scheduled for Thursday September 28th)
o Driveway
access restored to residents (Anticipate by Friday, September 29th)
·
Work to be performed along Hudson Road, York
Road, and Raleigh Road (south end to York Road):
o Continue
rough grading and installation of topsoil behind curb & gutter
o Complete
asphalt driveway restorations.
o Sod
installation scheduled for early October once remaining curb & gutter is
completed along Raleigh Road south of Drake Road.
·
Complete roadway excavation and installation of
base course along Baffin Road
o Anticipate
all roadway excavation and installation of base course to be completed by the
end of week for entire project.
The 1st phase of concrete curb & gutter and
asphalt pavement installation has been completed. This is a significant
project milestone for that area because the amount of dust is greatly reduced
and a smooth driving surface is provided.
The 2nd phase of concrete curb & gutter and
asphalt pavement will begin next week along Raleigh Road from York Road to
approximately 200 feet north of Drake Road. We request all residents in this
area have their vehicles removed from their driveways and garages by Tuesday,
September 19th at 7:00 AM. Access is anticipated to be restored
by Friday, September 29th. All residents affected have
received prior notification from the Village of Glenview. At this time,
residents are allowed to parking along York Road and Hudson Road where the
asphalt pavement was previously installed.
During this 2nd Phase the contractor will be
working extensively along Raleigh Road between Hudson Road and Drake Road. This
area becomes difficult to travel along as construction operations are
on-going. We ask that you are patient as you travel through the
area. As in the past, we may request you park your vehicles along Drake
Road if you need access during working hours. Additional information will be
provided should this request be made.
Roadway excavation and base course installation has been
completed along Raleigh Road. The final roadway to be completed is Baffin
Road. It is anticipated the remaining portion of Baffin Road will be completed
by the end of next week.
Thanks again to the residents along Phase 1 as you dealt
with the significant inconvenience of not having driveway access for
approximately 2 weeks. Thank you in advance for those residents along
Phase 2 that will be without driveway access starting on Tuesday, September 19th.
Due to the patience and understanding of all the residents, the project is
moving along as quickly as possible.