All concrete curb & gutter installed
·
First layer of asphalt pavement installed
throughout neighborhood
·
All driveway restorations completed (Brick
driveways are responsibility of homeowner)
·
Sod Restoration completed in southern portion of
neighborhood
·
Manhole adjustments to final elevation of new
asphalt surface
·
General site clean-up and demobilization of
equipment
Work Anticipated to be performed to complete project.
·
Complete landscape restoration with sod
·
Pave final surface layer of asphalt pavement
·
Final testing of underground utilities
·
Continue with general site clean-up
·
Perform miscellaneous tasks prior to asphalt
surface
·
Pavement marking as needed
We apologize for the extended delay in providing a Blog Post
for the project. Hopefully, the letters provided the Village have kept you
informed of the work on-going for the past few weeks.
The work is coming to an end as the construction season is
coming to a close. The contractor will continue to perform landscape
restorations with sod. The final layer of asphalt surface is scheduled
for the 2nd or 3rd week of November. Additional
information will be provided to the neighborhood once the dates are confirmed.
We are working with the contractor to schedule the work to minimize the
inconvenience to the residents. There will be lane closures and parking
restrictions during the days of asphalt paving; therefore, a detailed letter
will be provided regarding when they will be paving and where residents are
able to park and roadways that will be closed during the paving operations.
Thanks again for all your patience and understanding as the
project continues and the asphalt surface paving being the final major
construction activity.