Friday, October 27, 2017

Landscape Restoration On-Going. Asphalt Surface Paving Scheduled in 2 Weeks

Work Performed:
·         All concrete curb & gutter installed
·         First layer of asphalt pavement installed throughout neighborhood
·         All driveway restorations completed (Brick driveways are responsibility of homeowner)
·         Sod Restoration completed in southern portion of neighborhood
·         Manhole adjustments to final elevation of new asphalt surface
·         General site clean-up and demobilization of equipment          

Work Anticipated to be performed to complete project.
·         Complete landscape restoration with sod
·         Pave final surface layer of asphalt pavement
·         Final testing of underground utilities
·         Continue with general site clean-up
·         Perform miscellaneous tasks prior to asphalt surface
·         Pavement marking as needed

We apologize for the extended delay in providing a Blog Post for the project. Hopefully, the letters provided the Village have kept you informed of the work on-going for the past few weeks.

The work is coming to an end as the construction season is coming to a close. The contractor will continue to perform landscape restorations with sod.  The final layer of asphalt surface is scheduled for the 2nd or 3rd week of November. Additional information will be provided to the neighborhood once the dates are confirmed. We are working with the contractor to schedule the work to minimize the inconvenience to the residents. There will be lane closures and parking restrictions during the days of asphalt paving; therefore, a detailed letter will be provided regarding when they will be paving and where residents are able to park and roadways that will be closed during the paving operations.

Thanks again for all your patience and understanding as the project continues and the asphalt surface paving being the final major construction activity.

Monday, October 2, 2017

Phase 2: 1st Layer of Asphalt Paving Completed. Phase 3: Concrete Curb & Gutter Begins

Work Performed, September 25th to September 29th   
·         Work performed along Raleigh Road from York Road to 200 feet north of Drake Road (Phase 2 of 4)
o   Fine grade roadway base
o   Pave first layer of asphalt pavement
o   Complete asphalt driveway restoration
o   Grading and installation of topsoil
o   Driveway access restored to resident
·         Work performed along Hudson Road, York Road, and Raleigh Road (south end to York Road) (Phase 1 of 4)
o   Installation and grading of topsoil
·         Concrete curb & gutter and sidewalk repairs along Glenview Road.
·         AT&T was on-site to continue working on the relocation of the existing underground utility lines.

Work Anticipated to be performed, October 2nd to October 6th  
·         Work to be performed along Drake Road and easterly half of Baffin Road to Drake Road (Phase 3 of 4):
o   Access to driveways restricted starting on Monday, October 2nd
o   Install string line for curb & gutter
o   Pour concrete curb & gutter (Scheduled for Wednesday, October 4th )
o   Rough grading of landscape areas
o   Fine Grading of Roadway
o   Pave first layer of asphalt pavement (Scheduled for Monday, October 9th)
o   Driveway restorations
o   Access to driveways restored (by Tuesday, October 10th)
·         Sod Restoration to begin week of October 9th in the following locations.
o   Phase 1 of 4: Hudson Road, York Road, Raleigh Road (south end to York Road)
o   Phase 2 of 4: Raleigh Road from York Road to 200 feet north of Drake Road
·         Continue miscellaneous underground utility relocations and adjustments for sanitary sewer, storm sewer, and water main.

A 2nd phase of curb & gutter and first layer of asphalt pavement is completed. The third of four phases will begin on Monday.  The 3rd Phase includes Drake Road from Raleigh Road to Glenview Road and the easterly half of Baffin Road to Drake Road. Residents within this phase should have your vehicles removed from driveways and garages by 7:00 AM on Monday, October 2nd.  All affected residents have received prior notification from the Village of Glenview with parking suggestions. We anticipate driveway access will be restored by Tuesday, October 10th.

Residents within Phase 1 and Phase 2 of the curb & gutter / paving improvements are asked to contact your irrigation and/or brick driveway contractor to have your private improvements repaired or replaced.  The contractor will begin sod restoration in all areas south of Drake Road (Phase 1 and Phase 2) on Monday, October 9th. It would be a benefit to all involved to have those repairs completed prior to sod installation.

Thanks again to all the residents along Phase 2 that were without driveway access as the concrete curb & gutter and asphalt pavement was installed. Also, thanks to all those residents south of Drake Road that did not have access while working between Drake Road and Hudson Road.