Friday, October 27, 2017

Landscape Restoration On-Going. Asphalt Surface Paving Scheduled in 2 Weeks

Work Performed:
·         All concrete curb & gutter installed
·         First layer of asphalt pavement installed throughout neighborhood
·         All driveway restorations completed (Brick driveways are responsibility of homeowner)
·         Sod Restoration completed in southern portion of neighborhood
·         Manhole adjustments to final elevation of new asphalt surface
·         General site clean-up and demobilization of equipment          

Work Anticipated to be performed to complete project.
·         Complete landscape restoration with sod
·         Pave final surface layer of asphalt pavement
·         Final testing of underground utilities
·         Continue with general site clean-up
·         Perform miscellaneous tasks prior to asphalt surface
·         Pavement marking as needed

We apologize for the extended delay in providing a Blog Post for the project. Hopefully, the letters provided the Village have kept you informed of the work on-going for the past few weeks.

The work is coming to an end as the construction season is coming to a close. The contractor will continue to perform landscape restorations with sod.  The final layer of asphalt surface is scheduled for the 2nd or 3rd week of November. Additional information will be provided to the neighborhood once the dates are confirmed. We are working with the contractor to schedule the work to minimize the inconvenience to the residents. There will be lane closures and parking restrictions during the days of asphalt paving; therefore, a detailed letter will be provided regarding when they will be paving and where residents are able to park and roadways that will be closed during the paving operations.

Thanks again for all your patience and understanding as the project continues and the asphalt surface paving being the final major construction activity.