·
Work performed along Raleigh Road from York Road
to 200 feet north of Drake Road (Phase 2 of 4)
o Fine
grade roadway base
o Pave
first layer of asphalt pavement
o Complete
asphalt driveway restoration
o Grading
and installation of topsoil
o Driveway
access restored to resident
·
Work performed along Hudson Road, York Road, and
Raleigh Road (south end to York Road) (Phase 1 of 4)
o Installation
and grading of topsoil
·
Concrete curb & gutter and sidewalk repairs
along Glenview Road.
·
AT&T was on-site to continue working on the
relocation of the existing underground utility lines.
Work Anticipated to be performed, October 2nd
to October 6th
·
Work to be performed along Drake Road and
easterly half of Baffin Road to Drake Road (Phase 3 of 4):
o Access
to driveways restricted starting on Monday, October 2nd
o Install
string line for curb & gutter
o Pour
concrete curb & gutter (Scheduled for Wednesday, October 4th )
o Rough
grading of landscape areas
o Fine
Grading of Roadway
o Pave
first layer of asphalt pavement (Scheduled for Monday, October 9th)
o Driveway
restorations
o Access
to driveways restored (by Tuesday, October 10th)
·
Sod Restoration to begin week of October 9th
in the following locations.
o Phase
1 of 4: Hudson Road, York Road, Raleigh Road (south end to York Road)
o Phase
2 of 4: Raleigh Road from York Road to 200 feet north of Drake Road
·
Continue miscellaneous underground utility
relocations and adjustments for sanitary sewer, storm sewer, and water main.
A 2nd phase of curb & gutter and first layer
of asphalt pavement is completed. The third of four phases will begin on
Monday. The 3rd Phase includes Drake Road from Raleigh Road to
Glenview Road and the easterly half of Baffin Road to Drake Road. Residents
within this phase should have your vehicles removed from driveways and garages
by 7:00 AM on Monday, October 2nd. All affected residents have
received prior notification from the Village of Glenview with parking
suggestions. We anticipate driveway access will be restored by Tuesday, October
10th.
Residents within Phase 1 and Phase 2 of the curb &
gutter / paving improvements are asked to contact your irrigation and/or brick
driveway contractor to have your private improvements repaired or
replaced. The contractor will begin sod restoration in all areas south of
Drake Road (Phase 1 and Phase 2) on Monday, October 9th. It would be
a benefit to all involved to have those repairs completed prior to sod
installation.
Thanks again to all the residents along Phase 2 that were
without driveway access as the concrete curb & gutter and asphalt pavement
was installed. Also, thanks to all those residents south of Drake Road that did
not have access while working between Drake Road and Hudson Road.