Friday, September 22, 2017

Phase II Curb and Gutter Completed. Paving Next Week.

Work Performed, September 18th to September 22nd  
·         Work to be performed along Raleigh Road from York Road to 200 feet north of Drake Road:
o   Prep work and grading prior to concrete curb & gutter installation
o   Poured concrete curb & gutter
o   Rough grade landscape behind curb & gutter
o   Restoration of asphalt driveways (1st Layer of asphalt)
o   Restoration of concrete driveways
·         Work to be performed along Hudson Road, York Road, and Raleigh Road (south end to York Road):
o   Installation and grading of topsoil
·         Completed roadway excavation and installation of base course along Baffin Road.
o   All roadway excavation along entire project is now completed.
·         Continued miscellaneous underground utility relocations and adjustments for sanitary sewer, storm sewer, and water main.
·         Concrete curb & gutter and sidewalk repairs along Glenview Road.

Work Anticipated to be performed, September 25th to September 29th   
·         Work to be performed along Raleigh Road from York Road to 200 feet north of Drake Road:
o   Fine grade roadway base
o   Pave first layer of asphalt pavement (Scheduled for Wednesday, September 27th)
o   Complete asphalt driveway restoration
o   Grading and installation of topsoil
o   Driveway access restored to residents (Anticipate by Friday, September 29th)
·         Continued miscellaneous underground utility relocations and adjustments for sanitary sewer, storm sewer, and water main.
·         Landscape / Sod installation along Phase I and Phase II of concrete curb & gutter (South of Drake Road) is anticipated to begin the week of October 2nd.

The 2nd phase of concrete curb & gutter and asphalt pavement is on-going along Raleigh Road from York Road to approximately 200 feet north of Drake Road. Driveway access is anticipated to be restored by Friday, September 29th

Next week the contractor will be paving and fine grading along Raleigh Road between Hudson Road and Drake Road. Access south of Drake Road will be restricted during the following times:
·         Tuesday, September 26th from 7:00 AM to noon for fine grading
·         Wednesday, September 27th from 7:00 AM to 5:00 PM for paving.

Residents affected by this restricted access will be notified via letter from the Village of Glenview regarding times and parking options.

Thanks again for all those residents along Phase II of the concrete curb & gutter construction / asphalt paving as they are without driveway access.

Friday, September 15, 2017

Installation of Curb and Gutter Next Week for Phase 2 (Raleigh Road from York Road to 200 ft North of Drake Road.

Work Performed, September 11th to September 15th   
·         Work performed along Hudson Road, York Road, and Raleigh Road (south end to York Road):
o   Continued rough grading of landscape behind the curb & gutter
o   Fine graded aggregate base of roadway
o   Paved first binder layers of new asphalt pavement
o   Install 2nd layer of asphalt for driveway restorations.
o   Access to driveways restored (Friday, September 15th)
·         Completed roadway excavation and installation of base course along Raleigh Road from Baffin Road to Glenview Road
·         Continued roadway excavation and installation of base course along Baffin Road
·         Continued miscellaneous underground utility relocations and adjustments for sanitary sewer, storm sewer, and water main.
 
Work Anticipated to be performed, September 18th to September 22nd  
·         Work to be performed along Raleigh Road from York Road to 200 feet north of Drake Road:
o   Access to driveway restricted: Tuesday, September 19th at 7:00 AM
o   Installation of string line for concrete curb & gutter
o   Grading aggregate base under curb & gutter
o   Pour concrete curb & gutter (Scheduled for Thursday, September 21st)
o   Rough grade landscape behind curb & gutter
o   Restore asphalt driveways (1st Layer of asphalt)
o   Fine grade roadway base
o   Pave first layer of asphalt pavement (Scheduled for Thursday September 28th)
o   Driveway access restored to residents (Anticipate by Friday, September 29th)
·         Work to be performed along Hudson Road, York Road, and Raleigh Road (south end to York Road):
o   Continue rough grading and installation of topsoil behind curb & gutter
o   Complete asphalt driveway restorations.
o   Sod installation scheduled for early October once remaining curb & gutter is completed along Raleigh Road south of Drake Road.
·         Complete roadway excavation and installation of base course along Baffin Road
o   Anticipate all roadway excavation and installation of base course to be completed by the end of week for entire project.

The 1st phase of concrete curb & gutter and asphalt pavement installation has been completed.  This is a significant project milestone for that area because the amount of dust is greatly reduced and a smooth driving surface is provided.

The 2nd phase of concrete curb & gutter and asphalt pavement will begin next week along Raleigh Road from York Road to approximately 200 feet north of Drake Road. We request all residents in this area have their vehicles removed from their driveways and garages by Tuesday, September 19th at 7:00 AM. Access is anticipated to be restored by Friday, September 29th.  All residents affected have received prior notification from the Village of Glenview. At this time, residents are allowed to parking along York Road and Hudson Road where the asphalt pavement was previously installed.

During this 2nd Phase the contractor will be working extensively along Raleigh Road between Hudson Road and Drake Road. This area becomes difficult to travel along as construction operations are on-going.  We ask that you are patient as you travel through the area.  As in the past, we may request you park your vehicles along Drake Road if you need access during working hours. Additional information will be provided should this request be made.

Roadway excavation and base course installation has been completed along Raleigh Road.  The final roadway to be completed is Baffin Road. It is anticipated the remaining portion of Baffin Road will be completed by the end of next week.

Thanks again to the residents along Phase 1 as you dealt with the significant inconvenience of not having driveway access for approximately 2 weeks.  Thank you in advance for those residents along Phase 2 that will be without driveway access starting on Tuesday, September 19th. Due to the patience and understanding of all the residents, the project is moving along as quickly as possible.

Friday, September 8, 2017

Significant Work along Hudson, York, and Raleigh (South End to York) On-Going. Roadway Excavation Continues along Raleigh and Baffin.

Work Performed, September 5th to September 8th  
·         Work performed along Hudson Road, York Road, and Raleigh Road (south end to York Road):
o   Installation of string line for concrete curb & gutter
o   Fine graded aggregate base under concrete curb & gutter
o   Poured concrete curb & gutter
o   Asphalt driveway restorations (1st layer only)
o   Started fine Grading of roadway
o   Started rough grading of landscape behind the curb & gutter
·         Completed roadway excavation and installation of base course along Drake Road from Baffin Road to Glenview Road
·         Continued roadway excavation and installation of base course along Raleigh Road from Drake Road to Baffin Road
·         Continued miscellaneous underground utility relocations and adjustments for sanitary sewer, storm sewer, and water main.

Work Anticipated to be performed, September 11th to September 15th
·         Work performed along Hudson Road, York Road, and Raleigh Road (south end to York Road):
o   Complete rough grading of landscape behind the curb & gutter
o   Complete fine grading aggregate base of roadway
o   Pave first binder layers of new asphalt pavement (Scheduled for Thursday, September 14th)
o   Install 2nd layer of asphalt for driveway restorations.
o   Access to driveways restored (Anticipated by Friday, September 15th)
·         Complete roadway excavation and installation of base course along Raleigh Road from Baffin Road to Glenview Road
·         Begin roadway excavation and installation of base course along Baffin Road from Glenview Road to Drake Road.

A significant amount of progress has been made along Hudson Road, York Road, and Raleigh Road (south end to York Road) this past week. We appreciate all the residents patience and understanding as access to their driveways has been restricted for the past week. If all goes as planned, access will be restored by Friday, September 15th.  Next week a major milestone will be accomplished on this section of the roadway, paving the first layer of asphalt pavement. Once this work is performed, the amount of dust will be greatly reduced, a smooth driving surface will be provided, and access to driveways will be restored.

Roadway excavation will continue along Raleigh Road and Drake Road. Depending on work progress, all roadway excavation might be completed by the end of next week throughout the neighborhood.

During the week of September 18th, the 2nd stage of concrete curb & gutter, grading, and asphalt pavement will begin along Raleigh Road and Drake Road. The residents along those roadways will be without access to their driveways for approximately 2 weeks. Exact limits of work to be performed is being coordinated. Residents will be notified next week regarding location and timeframe for driveway restrictions as well as parking instructions.

Thanks again to all the residents and visitors of the neighborhood for dealing with the inconveniences that come with roadway reconstruction. Your patience and understanding is greatly appreciated.

Friday, September 1, 2017

Curb & Gutter on York, Hudson, and south end of Raleigh. Major Storm Sewer Improvements Completed. Roadway Excavation Continues on Drake and Baffin

Work Performed, August 28th to September 1st
·         Completed storm sewer installation along Baffin Road
·         Performed miscellaneous adjustments to underground utilities in preparation for concrete curb & gutter installation and roadway excavation.
·         Roadway excavation and installation of base course along Raleigh Road from Hudson Road to north of Drake Road
·         Roadway excavation and installation of base course along Drake Road from Raleigh Road to north of Baffin Road
·         AT&T performing permanent relocations of underground conduit and wire along Hudson Road and York Road 

Work Anticipated to be performed, September 5th to September 8th  
·         No work planned over weekend or Monday, September 4th in observance of Labor Day
·         Work along Hudson Road, York Road, and Raleigh Road (south end to York Road):
o   Tuesday, September 5th at 7:00 AM - Access to driveways restricted
o   Installation of string line for concrete curb & gutter
o   Fine grading of aggregate base under concrete curb & gutter
o   Pour concrete curb & gutter (scheduled for Wednesday, September 6th )
o   Rough grading of landscape behind the curb & gutter
o   Asphalt and concrete driveway restorations
o   Fine Grading of roadway (Week of September 11th)
o   Pave first binder layers of new asphalt pavement (Scheduled for Wednesday, September 13th)
o   Access to driveways restored (Anticipated by Friday, September 15th)
·         Complete roadway excavation and installation of base course along Drake Road from Baffin Road to Glenview Road
·         Perform roadway excavation and installation of base course along Baffin Road.
·         Continue with miscellaneous underground utility relocations and adjustments for sanitary sewer, storm sewer, and water main.
·         AT&T to begin permanent relocation of underground wire in conflict with proposed improvements.

Starting on Tuesday, September 5th, the contractor will begin concrete curb & gutter installation along Hudson Road, York Road, and Raleigh Road (South end to York Road). During this time, driveway access will be restricted for approximately 10 days while the concrete curb & gutter is poured, the concrete is allowed proper time to cure, the roadway is graded, driveways are restored, and the first layers of asphalt pavement are paved. See the anticipated work to be performed and schedule above.  Please have all vehicles removed from your driveways and garages by Tuesday, September 5th at 7:00 AM.  Once the concrete curb & gutter is poured, you will be able to park in front of your home after working hours (5:00 PM to 7:00AM) if you need closer access to deliver groceries or other items.  Please ensure to have your vehicles removed from the roadway prior to 7:00 AM. Daytime and overnight parking is available along Raleigh Road on the east side of the street or any other streets within the neighborhood. It is anticipated driveway access will be restored by Friday, September 15th.

Thanks in advance for all those residents along York Road, Hudson Road, and Raleigh Road from the south end to York Road that will be without driveway access for approximately 10 days. Your patience and understanding is greatly appreciated.