Friday, September 22, 2017

Phase II Curb and Gutter Completed. Paving Next Week.

Work Performed, September 18th to September 22nd  
·         Work to be performed along Raleigh Road from York Road to 200 feet north of Drake Road:
o   Prep work and grading prior to concrete curb & gutter installation
o   Poured concrete curb & gutter
o   Rough grade landscape behind curb & gutter
o   Restoration of asphalt driveways (1st Layer of asphalt)
o   Restoration of concrete driveways
·         Work to be performed along Hudson Road, York Road, and Raleigh Road (south end to York Road):
o   Installation and grading of topsoil
·         Completed roadway excavation and installation of base course along Baffin Road.
o   All roadway excavation along entire project is now completed.
·         Continued miscellaneous underground utility relocations and adjustments for sanitary sewer, storm sewer, and water main.
·         Concrete curb & gutter and sidewalk repairs along Glenview Road.

Work Anticipated to be performed, September 25th to September 29th   
·         Work to be performed along Raleigh Road from York Road to 200 feet north of Drake Road:
o   Fine grade roadway base
o   Pave first layer of asphalt pavement (Scheduled for Wednesday, September 27th)
o   Complete asphalt driveway restoration
o   Grading and installation of topsoil
o   Driveway access restored to residents (Anticipate by Friday, September 29th)
·         Continued miscellaneous underground utility relocations and adjustments for sanitary sewer, storm sewer, and water main.
·         Landscape / Sod installation along Phase I and Phase II of concrete curb & gutter (South of Drake Road) is anticipated to begin the week of October 2nd.

The 2nd phase of concrete curb & gutter and asphalt pavement is on-going along Raleigh Road from York Road to approximately 200 feet north of Drake Road. Driveway access is anticipated to be restored by Friday, September 29th

Next week the contractor will be paving and fine grading along Raleigh Road between Hudson Road and Drake Road. Access south of Drake Road will be restricted during the following times:
·         Tuesday, September 26th from 7:00 AM to noon for fine grading
·         Wednesday, September 27th from 7:00 AM to 5:00 PM for paving.

Residents affected by this restricted access will be notified via letter from the Village of Glenview regarding times and parking options.

Thanks again for all those residents along Phase II of the concrete curb & gutter construction / asphalt paving as they are without driveway access.