Work to be performed along Raleigh Road from
York Road to 200 feet north of Drake Road:
o Prep
work and grading prior to concrete curb & gutter installation
o Poured
concrete curb & gutter
o Rough
grade landscape behind curb & gutter
o Restoration
of asphalt driveways (1st Layer of asphalt)
o Restoration
of concrete driveways
·
Work to be performed along Hudson Road, York
Road, and Raleigh Road (south end to York Road):
o Installation
and grading of topsoil
·
Completed roadway excavation and installation of
base course along Baffin Road.
o All
roadway excavation along entire project is now completed.
·
Continued miscellaneous underground utility
relocations and adjustments for sanitary sewer, storm sewer, and water main.
·
Concrete curb & gutter and sidewalk repairs
along Glenview Road.
Work Anticipated to be performed, September 25th
to September 29th
·
Work to be performed along Raleigh Road from
York Road to 200 feet north of Drake Road:
o Fine
grade roadway base
o Pave
first layer of asphalt pavement (Scheduled for Wednesday, September 27th)
o Complete
asphalt driveway restoration
o Grading
and installation of topsoil
o Driveway
access restored to residents (Anticipate by Friday, September 29th)
·
Continued miscellaneous underground utility
relocations and adjustments for sanitary sewer, storm sewer, and water main.
·
Landscape / Sod installation along Phase I and
Phase II of concrete curb & gutter (South of Drake Road) is anticipated to
begin the week of October 2nd.
The 2nd phase of concrete curb & gutter and
asphalt pavement is on-going along Raleigh Road from York Road to approximately
200 feet north of Drake Road. Driveway access is anticipated to be restored by
Friday, September 29th.
Next week the contractor will be paving and fine grading
along Raleigh Road between Hudson Road and Drake Road. Access south of Drake
Road will be restricted during the following times:
·
Tuesday, September 26th from 7:00
AM to noon for fine grading
·
Wednesday, September 27th from
7:00 AM to 5:00 PM for paving.
Residents affected by this restricted access will be
notified via letter from the Village of Glenview regarding times and parking
options.
Thanks again for all those residents along Phase II of the
concrete curb & gutter construction / asphalt paving as they are without
driveway access.