Work Performed, August 28th to September 1st
·         Completed storm sewer installation along Baffin Road
·         Performed miscellaneous adjustments to underground utilities in preparation for concrete curb & gutter installation and roadway excavation.
·         Roadway excavation and installation of base course along Raleigh Road from Hudson Road to north of Drake Road
·         Roadway excavation and installation of base course along Drake Road from Raleigh Road to north of Baffin Road
·         AT&T performing permanent relocations of underground conduit and wire along Hudson Road and York Road 

Work Anticipated to be performed, September 5th to September 8th  
·         No work planned over weekend or Monday, September 4th in observance of Labor Day
·         Work along Hudson Road, York Road, and Raleigh Road (south end to York Road):
o   Tuesday, September 5th at 7:00 AM - Access to driveways restricted
o   Installation of string line for concrete curb & gutter
o   Fine grading of aggregate base under concrete curb & gutter
o   Pour concrete curb & gutter (scheduled for Wednesday, September 6th )
o   Rough grading of landscape behind the curb & gutter
o   Asphalt and concrete driveway restorations
o   Fine Grading of roadway (Week of September 11th)
o   Pave first binder layers of new asphalt pavement (Scheduled for Wednesday, September 13th)
o   Access to driveways restored (Anticipated by Friday, September 15th)
·         Complete roadway excavation and installation of base course along Drake Road from Baffin Road to Glenview Road
·         Perform roadway excavation and installation of base course along Baffin Road.
·         Continue with miscellaneous underground utility relocations and adjustments for sanitary sewer, storm sewer, and water main.
·         AT&T to begin permanent relocation of underground wire in conflict with proposed improvements.

Starting on Tuesday, September 5th, the contractor will begin concrete curb & gutter installation along Hudson Road, York Road, and Raleigh Road (South end to York Road). During this time, driveway access will be restricted for approximately 10 days while the concrete curb & gutter is poured, the concrete is allowed proper time to cure, the roadway is graded, driveways are restored, and the first layers of asphalt pavement are paved. See the anticipated work to be performed and schedule above.  Please have all vehicles removed from your driveways and garages by Tuesday, September 5th at 7:00 AM.  Once the concrete curb & gutter is poured, you will be able to park in front of your home after working hours (5:00 PM to 7:00AM) if you need closer access to deliver groceries or other items.  Please ensure to have your vehicles removed from the roadway prior to 7:00 AM. Daytime and overnight parking is available along Raleigh Road on the east side of the street or any other streets within the neighborhood. It is anticipated driveway access will be restored by Friday, September 15th.

Thanks in advance for all those residents along York Road, Hudson Road, and Raleigh Road from the south end to York Road that will be without driveway access for approximately 10 days. Your patience and understanding is greatly appreciated.