Work performed along Hudson Road, York Road, and
Raleigh Road (south end to York Road):
o Installation
of string line for concrete curb & gutter
o Fine
graded aggregate base under concrete curb & gutter
o Poured
concrete curb & gutter
o Asphalt
driveway restorations (1st layer only)
o Started
fine Grading of roadway
o Started
rough grading of landscape behind the curb & gutter
·
Completed roadway excavation and installation of
base course along Drake Road from Baffin Road to Glenview Road
·
Continued roadway excavation and installation of
base course along Raleigh Road from Drake Road to Baffin Road
·
Continued miscellaneous underground utility relocations
and adjustments for sanitary sewer, storm sewer, and water main.
Work Anticipated to be performed, September 11th to September 15th
·
Work performed along Hudson Road, York Road, and
Raleigh Road (south end to York Road):
o Complete
rough grading of landscape behind the curb & gutter
o Complete
fine grading aggregate base of roadway
o Pave
first binder layers of new asphalt pavement (Scheduled for Thursday, September
14th)
o Install
2nd layer of asphalt for driveway restorations.
o Access
to driveways restored (Anticipated by Friday, September 15th)
·
Complete roadway excavation and installation of
base course along Raleigh Road from Baffin Road to Glenview Road
·
Begin roadway excavation and installation of
base course along Baffin Road from Glenview Road to Drake Road.
A significant amount of progress has been made along Hudson
Road, York Road, and Raleigh Road (south end to York Road) this past week. We
appreciate all the residents patience and understanding as access to their
driveways has been restricted for the past week. If all goes as planned, access
will be restored by Friday, September 15th. Next week a major
milestone will be accomplished on this section of the roadway, paving the first
layer of asphalt pavement. Once this work is performed, the amount of dust will
be greatly reduced, a smooth driving surface will be provided, and access to
driveways will be restored.
Roadway excavation will continue along Raleigh Road and
Drake Road. Depending on work progress, all roadway excavation might be
completed by the end of next week throughout the neighborhood.
During the week of September 18th, the 2nd
stage of concrete curb & gutter, grading, and asphalt pavement will begin
along Raleigh Road and Drake Road. The residents along those roadways will be
without access to their driveways for approximately 2 weeks. Exact limits of
work to be performed is being coordinated. Residents will be notified next
week regarding location and timeframe for driveway restrictions as well as
parking instructions.
Thanks again to all the residents and visitors of the
neighborhood for dealing with the inconveniences that come with roadway
reconstruction. Your patience and understanding is greatly appreciated.