Friday, September 8, 2017

Significant Work along Hudson, York, and Raleigh (South End to York) On-Going. Roadway Excavation Continues along Raleigh and Baffin.

Work Performed, September 5th to September 8th  
·         Work performed along Hudson Road, York Road, and Raleigh Road (south end to York Road):
o   Installation of string line for concrete curb & gutter
o   Fine graded aggregate base under concrete curb & gutter
o   Poured concrete curb & gutter
o   Asphalt driveway restorations (1st layer only)
o   Started fine Grading of roadway
o   Started rough grading of landscape behind the curb & gutter
·         Completed roadway excavation and installation of base course along Drake Road from Baffin Road to Glenview Road
·         Continued roadway excavation and installation of base course along Raleigh Road from Drake Road to Baffin Road
·         Continued miscellaneous underground utility relocations and adjustments for sanitary sewer, storm sewer, and water main.

Work Anticipated to be performed, September 11th to September 15th
·         Work performed along Hudson Road, York Road, and Raleigh Road (south end to York Road):
o   Complete rough grading of landscape behind the curb & gutter
o   Complete fine grading aggregate base of roadway
o   Pave first binder layers of new asphalt pavement (Scheduled for Thursday, September 14th)
o   Install 2nd layer of asphalt for driveway restorations.
o   Access to driveways restored (Anticipated by Friday, September 15th)
·         Complete roadway excavation and installation of base course along Raleigh Road from Baffin Road to Glenview Road
·         Begin roadway excavation and installation of base course along Baffin Road from Glenview Road to Drake Road.

A significant amount of progress has been made along Hudson Road, York Road, and Raleigh Road (south end to York Road) this past week. We appreciate all the residents patience and understanding as access to their driveways has been restricted for the past week. If all goes as planned, access will be restored by Friday, September 15th.  Next week a major milestone will be accomplished on this section of the roadway, paving the first layer of asphalt pavement. Once this work is performed, the amount of dust will be greatly reduced, a smooth driving surface will be provided, and access to driveways will be restored.

Roadway excavation will continue along Raleigh Road and Drake Road. Depending on work progress, all roadway excavation might be completed by the end of next week throughout the neighborhood.

During the week of September 18th, the 2nd stage of concrete curb & gutter, grading, and asphalt pavement will begin along Raleigh Road and Drake Road. The residents along those roadways will be without access to their driveways for approximately 2 weeks. Exact limits of work to be performed is being coordinated. Residents will be notified next week regarding location and timeframe for driveway restrictions as well as parking instructions.

Thanks again to all the residents and visitors of the neighborhood for dealing with the inconveniences that come with roadway reconstruction. Your patience and understanding is greatly appreciated.