Friday, September 15, 2017

Installation of Curb and Gutter Next Week for Phase 2 (Raleigh Road from York Road to 200 ft North of Drake Road.

Work Performed, September 11th to September 15th   
·         Work performed along Hudson Road, York Road, and Raleigh Road (south end to York Road):
o   Continued rough grading of landscape behind the curb & gutter
o   Fine graded aggregate base of roadway
o   Paved first binder layers of new asphalt pavement
o   Install 2nd layer of asphalt for driveway restorations.
o   Access to driveways restored (Friday, September 15th)
·         Completed roadway excavation and installation of base course along Raleigh Road from Baffin Road to Glenview Road
·         Continued roadway excavation and installation of base course along Baffin Road
·         Continued miscellaneous underground utility relocations and adjustments for sanitary sewer, storm sewer, and water main.
 
Work Anticipated to be performed, September 18th to September 22nd  
·         Work to be performed along Raleigh Road from York Road to 200 feet north of Drake Road:
o   Access to driveway restricted: Tuesday, September 19th at 7:00 AM
o   Installation of string line for concrete curb & gutter
o   Grading aggregate base under curb & gutter
o   Pour concrete curb & gutter (Scheduled for Thursday, September 21st)
o   Rough grade landscape behind curb & gutter
o   Restore asphalt driveways (1st Layer of asphalt)
o   Fine grade roadway base
o   Pave first layer of asphalt pavement (Scheduled for Thursday September 28th)
o   Driveway access restored to residents (Anticipate by Friday, September 29th)
·         Work to be performed along Hudson Road, York Road, and Raleigh Road (south end to York Road):
o   Continue rough grading and installation of topsoil behind curb & gutter
o   Complete asphalt driveway restorations.
o   Sod installation scheduled for early October once remaining curb & gutter is completed along Raleigh Road south of Drake Road.
·         Complete roadway excavation and installation of base course along Baffin Road
o   Anticipate all roadway excavation and installation of base course to be completed by the end of week for entire project.

The 1st phase of concrete curb & gutter and asphalt pavement installation has been completed.  This is a significant project milestone for that area because the amount of dust is greatly reduced and a smooth driving surface is provided.

The 2nd phase of concrete curb & gutter and asphalt pavement will begin next week along Raleigh Road from York Road to approximately 200 feet north of Drake Road. We request all residents in this area have their vehicles removed from their driveways and garages by Tuesday, September 19th at 7:00 AM. Access is anticipated to be restored by Friday, September 29th.  All residents affected have received prior notification from the Village of Glenview. At this time, residents are allowed to parking along York Road and Hudson Road where the asphalt pavement was previously installed.

During this 2nd Phase the contractor will be working extensively along Raleigh Road between Hudson Road and Drake Road. This area becomes difficult to travel along as construction operations are on-going.  We ask that you are patient as you travel through the area.  As in the past, we may request you park your vehicles along Drake Road if you need access during working hours. Additional information will be provided should this request be made.

Roadway excavation and base course installation has been completed along Raleigh Road.  The final roadway to be completed is Baffin Road. It is anticipated the remaining portion of Baffin Road will be completed by the end of next week.

Thanks again to the residents along Phase 1 as you dealt with the significant inconvenience of not having driveway access for approximately 2 weeks.  Thank you in advance for those residents along Phase 2 that will be without driveway access starting on Tuesday, September 19th. Due to the patience and understanding of all the residents, the project is moving along as quickly as possible.