Saturday, July 29, 2017

Storm Sewer Installation Continues

Work Performed, July 24th to July 28th 
·         Continued with storm sewer installation along Raleigh Road from Drake Road north to Glenview Road
·         Continued with storm sewer installation along Raleigh Road from Drake Road to the south
·         Started storm sewer installation along Baffin Road
·         Nicor Gas has completed making all the connections between the new gas main and each residence.

Work Anticipated to be performed, July 31st to August 4th 
·         Continue with storm sewer installation along Raleigh Road, Baffin Road, and Drake Road
·         Grind-in-place the existing pavement along York Road, Hudson Road, and Raleigh Road south of Hudson Road
·         Nicor to complete abandonments of existing gas main and services.

The contractor has continued installing storm sewer along Raleigh Road. Due to several conflicts within existing utility companies (ComEd, AT&T, and WOW!), the contractor will be moving around to different areas of the jobsite until the utilities in conflict are relocated.  It is anticipated the storm sewer will be completed by the 2nd week of August.

Once the storm sewer along Raleigh is completed, the contractor will begin roadway improvements on the south half of the project along Hudson Road and York Road. The first step will be to grind-in-place the existing pavement in the area where it was not previously completed. As roadway construction and excavation begins, it will be increasingly more difficult to travel along the roadways because the entire roadway width will be under construction. The Village will provide notices regarding anticipated timeframes for work along each section of roadway.

The roadway improvements will include removing the existing asphalt pavement, installing new gravel base materials, repair unstable areas of the existing materials under the roadway, new concrete curb & gutter, and new asphalt pavement.

Thanks again for all your understanding as construction continues.

Friday, July 21, 2017

Water Main 100% Complete. Continue with Storm Sewer Installation on Raleigh Road

Work Performed, July 17th to July 21st
·         Completed water service replacements along Drake Road
·         Made final connections between new water main and existing water main
·         Made final disconnection of existing water main at Glenview Road and Raleigh Road
·         Resumed storm sewer installation along Raleigh Road
·         Nicor Gas has completed gas main and service installation

Work Anticipated to be performed, July 24th to July 28th
·         Continue with storm sewer installation along Raleigh Road.
·         Make connections at each residence between gas meter at house and new gas service.

The water main work is now completed. All newly installed water mains are in service and all residences have a new water service transferred to the new water main.

Nicor Gas has completed installation of all the gas mains and services throughout the neighborhood.  The last work to be completed is connecting each home to the new gas main by installing a new meter and connecting to the existing piping at the home. This work can only be performed as it is scheduled by the resident. Please be sure to schedule an appointment as soon as possible so the old gas main can be retired and removed to avoid conflicts with the new storm sewer piping.  Your cooperation is greatly appreciated and will help ensure the project is completed as soon as possible.

Thanks again for all you cooperation.

Friday, July 14, 2017

Water Main Improvements Nearly Complete. Please Contact NICOR when Requested

Work Performed, July 10th to July 14th   
·         Performed water service replacements along Drake Road and Raleigh Road.

Work Anticipated to be performed, July 17th to July 21st    
·         Complete water service replacements along Drake Road
·         Final connections and disconnections to existing water main at Hudson Road & Raleigh Road, Glenview Road & Raleigh Road, and Glenview Road & Drake Road.
·         Begin storm sewer improvements along Raleigh Road starting near Drake Road and moving south to Hudson Road.
·         Nicor Gas continuing to install gas mains and services

The new water main installation and service replacements will be completed by the end of the next week. There are a few services yet to replace along with making the final disconnections / connections to the existing main at various intersections.  During the water main connections / disconnections, a limited number of residents will be without water. The Village of Glenview will notify each resident of the day and time which the water will be turned off prior to doing the work.

The contractor will then resume installing storm sewer along Raleigh Road during the middle of next week.

Nicor Gas has been replacing the gas main and services throughout the neighborhood. They will be contacting you to schedule a time to switch-over from your old service to the new service.  As work as progressed, more and more services are able to be switched from the old main to the new main.  This is becoming a critical point in the construction in which the old main needs to be removed to avoid conflicts with the new storm sewer, please contact Nicor as soon as possible after you are contacted to allow them to make the switch.  Your cooperation in this is greatly appreciated and will help in keeping the project moving forward without delays.

Thanks again for all your patience and understanding while living in a construction area throughout the neighborhood.

Saturday, July 1, 2017

Water Service Replacements On-Going

Work Performed, June 26th to June 30th  
·         Completed water main installation along Drake Road
·         Performed necessary testing and received approvals to place new water main into service along Raleigh Road and Baffin Road
·         Started performing necessary testing to place new water main into service along Drake Road
·         Water service replacements along Raleigh Road
·         Nicor continuing to replace gas mains and services.
·         Site clean-up prior to July 4th Weekend

Work Anticipated to be performed, July 3rd to July 7th   
·         No work scheduled to be performed on Monday, July 3rd or Tuesday, July 4th on-site
·         Complete water service replacements along Raleigh Road
·         Begin water service replacements along Baffin Road
·         Complete necessary testing and received necessary approvals to place newly installed water main into service along Drake Road
·         Begin water service replacements along Drake Road
·         Nicor Gas continuing to install gas mains and services

The contractor will continue water service replacements throughout the neighborhood. Water services will be replaced from the new water main to the existing valve and box located in front of each home. During the water service replacement, water to individual homes will be shut-off for approximately 2-3 hours while the transition from the old service to the new service is made. The contractor will notify each resident individually regarding the approximate time and day of the water shut-off prior to turning off the water.

Nicor Gas has been replacing the gas main and services throughout the neighborhood. They will be contacting you to schedule a time to switch-over from your old service to the new service. Please make contact with Nicor to schedule this switch-over as soon as possible once your notice is received.  Getting the old gas main abandoned as quickly as possible will help complete the project sooner. Please be on the look-out for these notices from Nicor Gas.

As stated in previous posts, since this project is funded by the Village of Glenview, construction will not be delayed due to the current shut-down of IDOT projects.

Have a safe and enjoyable July 4th Weekend.