Continued with storm sewer installation along
Drake Road and Baffin Road
o Majority
of storm sewer to be completed by end of the week.
o Storm
sewer and other underground utility adjustments will be made throughout the
remaining construction
·
Roadway excavation and installation of base
course along York Road to Raleigh Road
·
Roadway excavation and installation of base
course along Raleigh Road from south end to Hudson Road
Work Anticipated to be performed, August 21st
to August 25th
·
Continue with storm sewer installation on Baffin
Road
·
Continue with miscellaneous underground utility
relocations and adjustments for sanitary sewer, storm sewer, and water main.
·
Continue with roadway excavation along Raleigh
Road from Hudson Road to Drake Road
·
AT&T to begin permanent relocation of
underground wire in conflict with proposed improvements.
·
General site clean-up in preparation for Labor
Day Weekend.
Starting early next week, the contractor will be working
along Raleigh Road between Hudson Road and Drake Road. As in the past with work
in this area, we will request all residents south of Drake Road to relocate
their vehicles during working hours as the roadway is excavated and will not be
travelable. Residents affected have been notified of exact dates and
instructions for parking prior this section of roadway being closed.
Directly following Labor Day Weekend, on Tuesday, September
5th, the contractor will begin concrete curb & gutter
installation along Hudson Road and York Road. During this time, driveway access
will be restricted for approximately 10 days while the concrete curb &
gutter is poured, the concrete is allowed proper time to cure, the roadway is
graded, driveways are restored, and the first layers of asphalt pavement are
paved. Additional notices will be provided by the Village.
Thanks in advance for all those residents south of Drake
Road as they deal with not having direct access to their homes during working
hours for a few days next week.