Storm sewer installation along Baffin Road and
Drake Road.
·
Roadway excavation and installation of aggregate
base course along Hudson Road and York Road
·
Temporary relocation of AT&T underground
wires in conflict with work to be performed
·
Relocation of sanitary sewer clean-outs in
conflict with proposed concrete curb & gutter
·
Adjustment of existing sanitary sewer manholes
requiring excavation.
Work Anticipated to be performed, August 21st
to August 25th
·
Continue with storm sewer installation along
Drake Road and Baffin Road
·
Continue with miscellaneous underground utility
relocations and adjustments for sanitary sewer, storm sewer, and water main.
·
Complete roadway excavation and installation of
aggregate base along York Road
·
Begin roadway excavation along Raleigh Road from
south end to Drake Road.
·
AT&T to begin permanent relocation of
underground wire in conflict with proposed improvements.
The contractor has continued to work on the storm sewer
while also performing other underground utility relocations within the areas
that are being excavated for roadway improvements. It was initially thought the
storm sewer would be installed by the end of this week; however, since they
have been doing other work as well, this is delayed slightly.
Currently, we anticipate the underground utility
improvements to be completed by Labor Day. Additionally, following the
Labor Day weekend, we anticipate concrete curb & gutter to begin along York
Road and Hudson Road.
Either later next week, or early the week of August 28th,
the contractor will be working along Raleigh Road between Hudson Road and Drake
Road. As in the past with work in this area, we will request all residents
south of Drake Road to relocate their vehicles during working hours as the
roadway is excavated and will not be travelable. Residents affected will be
notified of exact dates and instructions to parking prior this section of
roadway being closed.
Thanks again for all your patience and understanding as
construction continues.