Storm sewer installation along Baffin Road, Raleigh
Road, and Drake Road.
·
Driveway removals along Raleigh Road, York Road
and Hudson Road in preparation for roadway improvements
·
Grind-in-place the existing pavement along York
Road, Hudson Road, and Raleigh Road south of Hudson Road
·
Staking of proposed roadway improvements along
York Road, Hudson Road, and Raleigh Road.
·
Nicor completed gas main and service
replacements for entire neighborhood.
·
ComEd performed utility relocations to avoid
conflicts
·
WOW! performed utility relocations to avoid
conflicts
Work Anticipated to be performed, August 14th
to August 18th
·
Complete storm sewer installation for the entire
project.
·
Begin roadway improvements along Hudson Road and
York Road
The underground utility improvements (sanitary sewer, water
main, and storm sewer) of the project are nearly completed. It is anticipated
the work will be completed by the end of this week. There are likely some minor
adjustments and work to be completed following this week, but the major
construction of these items will be completed.
The contractor is beginning the roadway improvements along
Hudson Road and York Road this week. The roadway improvements will include
removing the existing asphalt pavement, installing new gravel base materials,
repair unstable areas of the existing materials under the roadway, new concrete
curb & gutter, and new asphalt pavement. Likely, the roadway excavation and
aggregate base course installation will be performed this week, with concrete
curb & gutter performed in the coming weeks.
Additional conflicts with utility company underground cables
were identified this week. The Village has been in contact with these companies
and requesting the cables be relocated and quickly as possible to prevent
further delays in the project.
Thanks again for all your patience and understanding as we
switch from the underground utility improvement phase to the roadway
improvement phase of the project.