·
Resident preconstruction meeting conducted.
Thanks to all of you that attended
·
Material Deliveries
·
Set-up Staging area on south end of project
Work Anticipated to be completed, May 1st to
May 5th
·
Grind-in-place the existing roadway on the north
end of the project
·
Continue with material deliveries
·
Finalize staging area on south end of the
project
·
Mobilization of equipment
Thanks to all of you that attending the Resident
Preconstruction Meeting last Monday evening. We hope that you found it
informative and well worth your time.
Next week, the contractor will begin mobilization of
equipment and work in preparation for heavy underground utility construction
starting the week of May 8th. The contractor will grind-in-place the
existing roadway along Raleigh Road from Hudson Road to Glenview Road, Drake
Road from Raleigh Road to Glenview Road, and Baffin Road from Drake Road to
Raleigh Road. The grind-in-place work is anticipated to take 1-day and
you will be able to drive on it soon after it is completed. However, during the
construction, the section of roadway being worked on will be difficult to drive
on and use of an alternative route is suggested.
As the week continues, you will see periods of construction activity
with the major work starting on Monday, May 8th.