Sanitary sewer replacements on Raleigh Road
·
Sanitary sewer replacements on Drake Road
·
Install storm sewer at intersection of Raleigh
Road and York Road
·
Install storm sewer along York Road
·
Nicor Gas started installing new gas main
Work Anticipated to be performed, June 5th to
June 9th
·
Sanitary sewer improvements on Raleigh Road to
be completed
·
Resume water main installation along Raleigh
Road from Baffin Road to Hudson Road
·
Nicor Gas continuing to install gas mains.
Thanks again for all your patience during construction. We
understand how difficult it is to live within a construction area dealing with
the dust and travel delays.
As the work continues south, keeping travel lanes open along
Raleigh Road between Drake Road and Hudson Road will be difficult. It is
anticipated Raleigh Road will be closed to traffic during the day from Drake
Road to the south, including Hudson Road and York Road. We will request
vehicles be parked north of the construction area with access before and after
working hours. This will likely occur several times during construction
due to utility construction, roadway reconstruction, concrete curb & gutter
construction, and asphalt paving. We understand the significant
inconvenience this will cause, so we are working to minimize to the greatest
extent possible. Additional information regarding these potential roadway
closures will be forthcoming.